top bg
This schedule is tentative and subject to change.

Action Item Date
Award consultant contract for preliminary survey May 13, 2020
Authorize preparation of preliminary report October 28, 2020
Authorize preparation of plans and specifications April 14, 2021
Neighborhood Meeting No. 1 October 2021
Approve preliminary report, public improvement hearing and order project October 2021
Open bids December 2021
Neighborhood Meeting No. 3 February 2022
Assessment hearing and award contract March 2022
Neighborhood Meeting No. 4 - Construction Information April 2022
Begin construction April 2022
Complete construction June 2023